|
|
| [Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] |
************************************************************
NTSB PRESS RELEASE
************************************************************
National Transportation Safety Board
Washington, DC 20594
FOR IMMEDIATE RELEASE: May 31, 2006
SB-06-33
************************************************************
NTSB DETERMINES POOR PLANNING AND INADEQUATE BRACING
CAUSED DEADLY HIGHWAY BRIDGE GIRDER COLLAPSE
************************************************************
Washington, D.C. -- In a report adopted today, the National
Transportation Safety Board determined that poor
construction planning and execution led to the failure of a
temporary bracing system for a bridge girder being installed
above Interstate 70 (I-70) in Golden, Colorado, causing the
girder to collapse onto a passenger vehicle on I-70, killing
three people. The Board cited as contributing factors the
lack of uniform, consistent bracing standards and the
Colorado Department of Transportation's (CDOT's) narrow
definition of falsework, which did not include lateral
bracing. Also contributing to the accident was CDOT's
failure to effectively oversee safety-critical contract
work.
"This accident shows us just how important it is to
have very clear guidelines about what is required for safe
operations," stated NTSB Acting Chairman Mark V. Rosenker,
"Sometimes it seems like such common sense that we wonder
why we need these guidelines, and then we see an accident
like this one."
On the morning of May 15, 2004, a steel girder that
had been installed about 3 days earlier and secured with a
temporary bracing system, sagged into the eastbound lanes of
I-70 and struck a sport utility vehicle traveling along the
roadway. All three people in the vehicle, including a 2-
year-old child, were killed in the accident.
The girder had been installed as part of a bridge-
widening project managed by CDOT. To perform the
construction work, CDOT contracted with Asphalt Specialties,
Inc., which subcontracted the girder installation to Ridge
Erection Company, Inc.
Ridge's girder installation and bracing plan was
inadequate and was not prepared or reviewed by a Registered
Professional Engineer, nor was it required to be. The lack
of planning resulted in multiple problems for the Ridge crew
during the construction process carried out on the night of
May 11 to 12. The crew did not have the proper tools, and it
inadvertently began installing a section of the accident
girder backward. These situations delayed the projected work
for that night, so Ridge did not complete the work intended
for that night and had to secure the girder with a temporary
bracing system, expecting to complete the girder
installation work the next night. However, due to weather,
this work was postponed, so the girder remained secured with
the temporary bracing system for several days.
While constructing the temporary bracing system, Ridge
had experienced difficulty anchoring the bracing to the
severely degraded bridge deck pavement. Postaccident
examination also revealed that Ridge had installed the
girder out of plumb. The braces, originally intended to
secure a correctly installed girder for hours rather than
days, failed causing the girder to sag into the roadway.
As a result of its investigation, the Board
recommended that the Federal Highway Administration, the
Occupational Safety and Health Administration (OSHA), and
the American Association of State Highway and Transportation
Officials (AASHTO) work together to develop consistent
guidance and requirements for constructing such temporary
highway bracing and related structures, known as
"falsework," including that all falsework plans should be
prepared or approved by a Registered Professional Engineer.
The Board also cited CDOT's failure to oversee safety-
critical portions of the project because CDOT's on-site
supervisors were aware of the problems Ridge experienced but
did not question the adequacy of the work done by the
subcontractor. The Board recommended that AASHTO revise its
guidance concerning oversight conducted by highway
supervisory construction personnel to call for
prequalification of subcontractors; submission of engineer-
approved written plans for all construction, including
falsework; intervention when contractors or subcontractors
demonstrate a lack of competence; and monitoring of
temporary bracing systems until construction is completed.
A synopsis of the Board's report, including the
probable cause and recommendations, is available on the
Board's website, www.ntsb.gov. The Board's full report will
be available on the website in several weeks.
##
Media Contact: Lauren Peduzzi
peduzzi@xxxxxxxx
(202) 314-6100
************************************************************
This message is delivered to you as a free service from the
National Transportation Safety Board.
You may unsubscribe at any time at
http://www.ntsb.gov/registration/registration.htm
An archive of press releases is available at
http://www.ntsb.gov/pressrel/pressrel.htm
Current job opportunities with the NTSB are listed at
http://www.ntsb.gov/vacancies/listing.htm
For questions/problems, contact pubinq@xxxxxxxx
[FAA] [STB] [USDA] [Photography] [Yosemite Camping] [Hot Springs] [Steve's Art] [SB Lupus] [Railroad] [FDA News]