April 3, 2009
George H. Diller
Kennedy Space Center, Fla.
321-867-2468
george.h.diller@nasa.gov
STATUS REPORT: ELV-040309
EXPENDABLE LAUNCH VEHICLE STATUS REPORT
Mission: Geostationary Operational Environmental Satellite (GOES-O)
Launch Vehicle: Delta IV
Launch Pad: Launch Complex 37, Cape Canaveral Air Force Station, Fla.
Launch Date: No earlier than April 28, 2009
Launch Window: 6:24 - 7:24 p.m. EDT
A partial charging of the GOES-O spacecraft batteries has been
performed and a power command functional test of the spacecraft power
subsystem has been successfully completed. Spacecraft fueling
operations began with the loading of oxidizer into the onboard fuel
tanks on March 30. The hydrazine fuel was done on April 1.
Mating GOES-O to the Delta IV rocket payload attach fitting for flight
is planned for April 4 and will be followed by encapsulation into the
fairing on April 6. The move to Launch Complex 37 for mating to the
Delta IV is scheduled for April 14.
At Launch Complex 37, checkout of the Delta IV is on schedule. A
simulated flight test exercising the launch vehicle systems as they
will function during launch has been was successfully completed. The
"wet dress rehearsal," a countdown dress rehearsal with the rocket
fully fueled, is planned for April 8.
NASA has contracted with Boeing to build and launch the GOES-O
spacecraft. The NASA Launch Services Program at Kennedy is supporting
the launch in an advisory role. NASA spacecraft project management
for GOES-O is the responsibility of NASAâ??s Goddard Space Flight
Center. After launch, once Boeing and NASA have completed on-orbit
checkout and the spacecraft is operational, it will be turned over to
NOAA.
Mission: Lunar Reconnaissance Orbiter/Lunar Crater Observation and
Sensing Satellite (LRO/LCROSS)
Launch Vehicle: Atlas V
Launch Pad: Launch Complex 41, Cape Canaveral Air Force Station, Fla.
Launch Date: No earlier than June 2, 2009
Launch Window: TBD
The launch of LRO/LCROSS has been rescheduled to no earlier than June
2. This will enable sufficient time to be built back into the Atlas V
processing schedule to support launch. The processing schedule became
insufficient after the launch postponement of the Atlas V for the
non-NASA mission currently on the launch pad.
This week the LRO spacecraft team has been performing mission launch
rehearsals, liftoff through lunar insertion. The solar arrays are
planned for installation on April 8.
The LCROSS spacecraft team is performing electrical testing.
Previous status reports are available at:
http://www.nasa.gov/centers/kennedy/launchingrockets/status/index.html
-end-
To subscribe to the list, send a message to:
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov
[KSC Site]
[NASA News]
[NASA Science News]
[JPL]
[NTSB]
[Yosemite News]
[Hot Springs]
[Tuolumne Meadows Campground]
[STB]
[Deep Creek Forum]
[NSF]
[Cassini Status Reports]
[Telescopes]