May 13, 2005
Allard Beutel
Headquarters, Washington
(Phone: 202/358-4769)
Jessica Rye
Kennedy Space Center, Fla.
(Phone: 321/867-2468)
STATUS REPORT: S-051305
NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT
NASA's Space Shuttle fleet is housed and processed at Kennedy Space
Center (KSC), Fla.
Mission: STS-114 - 17th ISS Flight (LF1) - Multi-Purpose Logistics
Module
Vehicle: Discovery (OV-103)
Location: Launch Pad 39B
Launch Date: Launch Planning Window July 13 - 31, 2005
Launch Pad: 39B
Crew: Collins, Kelly, Noguchi, Robinson, Thomas, Lawrence and Camarda
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Work continues at Launch Pad 39B in preparation for an External Tank
(ET) tanking test scheduled for no earlier than May 19 for the
STS-114 mission to the International Space Station. Engineers and
technicians are adding instrumentation to the tank to help
troubleshoot two issues that arose during a tanking test on April 14.
The instrumentation will provide data to analyze the liquid hydrogen
sensors that gave intermittent readings and the liquid hydrogen
pressurization relief valve that cycled more times than standard
during last month's test.
The tanking test involves the ground operations team at Kennedy Space
Center filling the ET with liquid oxygen and liquid hydrogen fuel.
The team evaluates how the tank, orbiter, Solid Rocket Boosters
(SRBs) and ground systems perform under "cryo-load," when the tank is
filled with the two ultra-low temperature fuels. The tank filling and
draining portion of the test will take about 11 hours and includes a
simulated countdown through the T minus 31 second hold. However, the
total length of the test operations at KSC will take approximately 48
hours.
Following the tanking test, technicians will begin preparations for
rolling back Space Shuttle Discovery to the Vehicle Assembly Building
by the end of the month. Once there, orbiter Discovery will be
destacked (removed) from its ET and lowered into the transfer aisle.
In the Vehicle Assembly Building, preparations of ET-121 are currently
taking place in the checkout cell. Final checkout of the vent valve
assembly is complete. The change-out of the liquid oxygen and liquid
hydrogen diffusers is complete. Following the ET/SRB mate review next
week, the tank will be moved from the checkout cell and attached to
the SRBs in the integration cell.
Once in the integration cell, a new heater will be added to the
feedline bellows to minimize the potential for ice and frost buildup.
It will take about 24 days to perform the modification.
Mission: STS-121 - 18th ISS Flight (ULF1) - Multi-Purpose Logistics
Module
Vehicle: Atlantis (OV-104)
Location: Orbiter Processing Facility Bay 1
Launch Date: Lighted Launch Planning Window September 9 - 24, 2005
Launch Pad: 39B
Crew: Lindsey, Kelly, Sellers, Fossum, Nowak and Wilson
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Processing continues on Atlantis in Orbiter Processing Facility bay 1
for its mission, designated STS-121, to the International Space
Station. The vehicle is currently powered down in support of orbiter
electrical wiring and connector work. Forward-, midbody- and aft-area
closeouts continue.
Camera verification is complete on the Remote Manipulator System, or
Shuttle arm, in the payload bay. Payload bay door clearance checks
were successfully completed on the Orbiter Boom Sensor System on the
starboard side of the payload bay.
Nose and main landing gear cycles continue in preparation for the
landing gear functional test, scheduled for today. Thermal Protection
System tile installation is complete on the payload bay door hinge
area and technicians are performing tile bond verification.
Endeavour (OV-105)
Endeavour is in its Orbiter Major Modification period, which began in
December 2003.
Previous Space Shuttle processing status reports are available on the
Internet at:
http://www.nasa.gov/returntoflight
-end-
To subscribe to the list, send a message to:
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov
[KSC Site]
[NASA News]
[NASA Science News]
[JPL]
[NTSB]
[Yosemite News]
[Hot Springs]
[Tuolumne Meadows Campground]
[STB]
[Deep Creek Forum]
[NSF]
[Cassini Status Reports]
[Telescopes]