02.25.05
Jessica Rye
Kennedy Space Center, Fla.
(321) 867-6185
STATUS REPORT: S2-08
SPACE SHUTTLE PROCESSING STATUS REPORT
Note: NASA's Kennedy Space Center issues Space Shuttle Processing
Status Reports each week, and is the source for information regarding
processing activities associated with the vehicles and payloads. This
report does not necessarily reflect the chronological order of future
Space Shuttle missions. If you are a member of the media and would
like further information, visit
http://www.nasa.gov/centers/kennedy/news/index.html.
Mission: STS-114 - 17th ISS Flight (LF1) - Multi-Purpose Logistics
Module
Vehicle: Discovery (OV-103)
Location: Orbiter Processing Facility Bay 3
Launch Date: Launch Planning Window May 15 - June 3, 2005
Launch Pad: 39B
Crew: Collins, Kelly, Noguchi, Robinson, Thomas, Lawrence and Camarda
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
In Orbiter Processing Facility bay 3, orbiter system testing is 96
percent complete on Discovery for its mission, designated STS-114, to
the International Space Station. Final work and closeouts are
progressing well in preparation for Discovery's roll over to the
Vehicle Assembly Building mid-March.
The payload bay doors are scheduled to be closed on Monday for
installation of a few remaining door-hinge carrier panels. The
payload bay doors will then be opened to verify correct placement of
the carrier panels. Once this is complete, the payload bay doors will
be closed the final time next week for flight. Work continues on seal
installation on the main and nose landing-gear doors, and will be
followed by functional tests to ensure the proper compression of the
doors.
In the Vehicle Assembly Building, paint and cork repairs are complete
on the Solid Rocket Boosters' (SRBs) aft inactive stub ring, an
attach ring surrounding the booster located about 10 feet below the
External Tank (ET) attach point. The ET is scheduled to be moved from
the checkout cell to the integration cell and mated, or attached, to
the twin SRBs on Monday.
Mission: STS-121 - 18th ISS Flight (ULF1) - Multi-Purpose Logistics
Module/Crew Rotation
Vehicle: Atlantis (OV-104)
Location: Orbiter Processing Facility Bay 1
Launch Date: Launch Planning Window July 12 - July 31, 2005
Launch Pad: 39B
Crew: Lindsey, Kelly, Sellers, Fossum, Nowak and Wilson
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Technicians continue to process Atlantis in Orbiter Processing
Facility (OPF) bay 1 for its mission, designated STS-121, to the
International Space Station. Powered-up system testing continues with
water coolant loop No. 1 servicing and No.2 deservicing, fuel cell
leak checks, as well as Global Positioning System and orbiter docking
system testing.
The Remote Manipulator System, or Space Shuttle arm, was delivered to
the bay Thursday for installation into Atlantis' payload bay this
weekend. The Forward Reaction Control System was installed on the
vehicle Monday, and work continues on bolt installations. Rudder
Speed Brake installation is nearly complete, while seal installation
and Thermal Protection System blanket bonding on the vertical
stabilizer is ongoing.
Endeavour (OV-105)
On Tuesday, orbiter Endeavour moved from the OPF to the Florida Space
Authority's Reusable Launch Vehicle hangar at Kennedy Space Center.
While in the hangar, Endeavour will be tested to see how orbiters
respond to a new radar system that will be used to detect debris
during launch. In the OPF, work includes modifications to the bay and
platform validation. Endeavour will remain in the hangar for
approximately 30 days, then return to the OPF.
-end-
To subscribe to the list, send a message to:
ksc-subscribe@newsletters.nasa.gov
To remove your address from the list, send a message to:
ksc-unsubscribe@newsletters.nasa.gov
[KSC Site]
[NASA News]
[NASA Science News]
[JPL]
[NTSB]
[Yosemite News]
[Hot Springs]
[Tuolumne Meadows Campground]
[STB]
[Deep Creek Forum]
[NSF]
[Cassini Status Reports]
[Telescopes]