Cassini Significant Events 03/04/09 - 03/10/09
Title: Cassini Significant Events 03/04/09 -
03/10/09
Cassini Significant
Events
03/04/09 - 03/10/09
The most recent spacecraft telemetry was acquired on Mar. 10 from the
Deep Space Network tracking complex at Goldstone, California.
The Cassini spacecraft is in an excellent state of health.
Information on the present position and speed of the Cassini
spacecraft may be found on the "Present Position" page at:
http://saturn.jpl.nasa.gov/operations/present-position.cfm.
Wednesday, March 4 (DOY
063):
Attitude and Articulation Control Subsystem (AACS) engineers performed
annual calibration tests on the Cassini Inertial Reference Unit today.
Results of the test showed continuing normal performance.
Once this activity was complete, the Imaging Science Subsystem (ISS),
Composite Infrared Spectrometer (CIRS), and Visual and Infrared
Mapping Spectrometer (VIMS) observed the F-Ring, then the Ultraviolet
Imaging Spectrograph (UVIS) mapped the volatiles in the immediate
neighborhood of Enceladus in order to test the connection of volatile
changes to plume eruptions.
Although not an image acquired by Cassini, the Astronomy Picture of
the Day for Mar. 4 gave a good depiction of what Saturn currently
looks like through a telescope. At opposition on Mar. 8, Saturn
rises at sunset and sets at sunrise, offering many hours of viewing
enjoyment! If you don't have access to a telescope, contact one
of the 400 members of the Cassini Saturn Observation Campaign to find
out where a viewing event will take place near you. See
http://saturn.jpl.nasa.gov/Education/saturnobservation/volunteermembers/ and
http://antwrp.gsfc.nasa.gov/apod/ap090304.html
Thursday, March 5 (DOY 064):
How is it that at one moment Cassini can be found nearly at apoapsis,
the farthest point from Saturn in an orbit, and within a day, be at
periapsis, the closest point to Saturn in an orbit, when its orbital
period is around 16 days? Well, it is happening at the end of
March this year. On DOY-86, Mar. 27, the Titan 51 targeted flyby
will occur. Just a few hours later, apoapsis and the start of
orbit #107 would have occurred. However, because of the
gravitational influence of Titan during the flyby, Cassini's orbit is
modified such that apoapsis on the new Saturn centered orbit occurs
prior to the Titan encounter, on an orbit different from the one
Cassini actually flew. For orbit 107, on DOY-87, Mar. 28, Cassini is
now at the closest point to Saturn in that orbit. The above
scenario is unique in the history of the project and will not occur
again before the end of the extended mission. The fact that Cassini's
orbit about Saturn is very nearly circular at this time is what
enables this rather curious sequence of events.
Friday, March 6 (DOY 065):
An Uplink Readiness Review was held today which led to final approval
for the RCS thruster swap to the B branch.
Along with Orbit Trim Maneuver (OTM) #183, commands for the opening of
Latch Valve 41 (LV41) were sent to the spacecraft today. The
LV41 commands will execute on Mar. 10 and will enable the flow of
hydrazine to the B-branch thrusters.
Monday, March 9 (DOY 068):
A kick-off meeting was held today as part of the Science Operations
Plan (SOP) process for S53. In addition, all participating teams
delivered files and products for the Port 1 delivery as part of the
SOP process for S52.
Orbit Trim Maneuver (OTM) #183 was performed today. This is the
maneuver setting up for the Titan 51 encounter on Mar. 27. The
main engine burn began at 2:30 AM PDT. Telemetry immediately after the
maneuver showed the burn duration was 29.88 seconds, giving a delta-V
of 5.02 m/s. All subsystems reported nominal performance after
the maneuver.
Following the execution of OTM-183, a red alarm was detected in
association with one of the temperature sensors on the main engine
combustion chamber, and it appears that one of the two redundant
sensors has failed. This will have no effect on the planned RCS swap
to the B side, nor to any future operation of the main engine. It does
mean that there is now one less level of redundancy in monitoring the
performance of the prime main engine.
Science observations today included a 3-hour observation by ISS, CIRS,
and UVIS to attempt to observe the illusive Rhea ring. An
additional six hours focused on Rhea will occur tomorrow. In
addition, The Cosmic Dust Analyzer (CDA) took data as Cassini passed
through the ring plane.
Tuesday, March 10 (DOY 069):
After LV-41 was verified open today via telemetry, several files were
sent to the spacecraft to set the catalyst bed heaters for the
B-branch to "Auto" or "ON" except for when the thruster
fires, deactivate the S48 background sequence, and load the
mini-background sequence that will execute from DOY 70-76. The
last two files will take effect Mar. 12, just prior to AACS branch
swap commanding when the B-branch will be made prime.
The next and final live update in S48 was for Enceladus on DOY-080.
After analyzing the orbit determination solution from DOY-067, Science
Planning has determined that an update to pointing is not necessary
and has recommended that the live update be cancelled.
------------------------
To unsubscribe from Cassini Spacecraft Updates or to subscribe with a
different email address, visit:
<http://saturn.jpl.nasa.gov/news/mailinglistsignup/ >
------------------------
This email address is not monitored. For comments and questions,
please contact Cassini Outreach at:
<http://saturn.jpl.nasa.gov/feedback/>
------------------------
Visit the JPL Cassini home page for more information about the Cassini
Project: <http://saturn.jpl.nasa.gov/>
------------------------
[NASA News]
[JPL Home]
[JPL News]
[NASA KSC]
[NTSB]
[Hot Springs]
[Yosemite News]
[NSF]
[NASA News]
[Bake Sale for NASA]
[Telescopes]